1 |
1st RING ROAD JAHRA GATE ROUND ABOUT |
MINISTRY |
AKTOR |
1/11/2010 |
30/06/2011 |
COMPLETED |
2 |
BOUBYAN SEAPORT PROJECT |
MINISTRY |
HYUNDAI |
1/3/2011 |
31/03/2014 |
COMPLETED |
3 |
MANPOWER LPG4 PROJECT |
KNPC |
MTC |
5/9/2011 |
31/12/2011 |
COMPLETED |
4 |
MANUAL EXCAVATION LPG4 TRAIN PROJECT |
KNPC |
MTC |
11/12/2011 |
31/05/2013 |
COMPLETED |
5 |
LPG4 TRAIN AT MAA REFINERY |
KNPC |
DAELIM |
5/4/2012 |
31/08/2015 |
COMPLETED |
6 |
TELEMETRY SYSTEM INSTALLATION FOR MONITORING &CONTROL OF CONSUMER NETWORK |
KOC |
DAELIM |
1/2/2013 |
31/08/2016 |
COMPLETED |
7 |
TILE LAYING,CABLE PULLING HENC KNPC |
KNPC |
MTC |
5/6/2013 |
30/09/2013 |
COMPLETED |
8 |
KNPC HALON PHASE OUT PROJECT |
KNPC |
HANWHA |
9/10/2013 |
18/03/2014 |
COMPLETED |
9 |
SCAFFOLDING WORK KOC&SHUAIBA TELEMETRY |
KNPC |
MTC |
23/06/2013 |
31/06/2014 |
COMPLETED |
10 |
LPG4 KNPC MAA REFINERY |
KNPC |
SBC |
1/3/2014 |
31/07/2014 |
COMPLETED |
11 |
KNPC NLTF PROJECT |
KNPC |
GS E & C |
4/11/2014 |
15/12/2014 |
COMPLETED |
12 |
MAA REF& MAB1 REF |
KNPC |
NSH |
1/12/2015 |
30/09/2016 |
COMPLETED |
13 |
MAB2 REF |
KNPC |
NSH |
1/9/2015 |
30/06/2016 |
COMPLETED |
14 |
SULPHUR HANDLING FACILITIES PROJECT(SHFP) |
KNPC |
AFCON |
24/11/2015 |
31/08/2016 |
COMPLETED |
15 |
SULPHUR HANDLING FACILITIES PROJECT MAA(SHFP) |
KNPC |
AL MAGWA |
1/10/2015 |
29/02/2016 |
COMPLETED |
16 |
SULPHUR HANDLING FACILITIES PROJECT(SHFP) |
KNPC |
GLOBAL ACCESS |
15/02/2016 |
29/02/2016 |
COMPLETED |
17 |
SCAFFOLDING INSTALLATION FOR B 18 MAA-CFP |
KNPC/td>
| AL KULAIB/ HOWON |
11/03/17 |
22/03/2017 |
COMPLETED |